The Christmas Ordering Timeline Every Importer Should Work Backwards From
Christmas is the only retail season with a hard deadline. A jumper that arrives in November still sells in January; a Christmas tree that arrives in December sells at a loss. Every year buyers discover this in October, and every year the same sequence of problems repeats: sampling delays, production queues, port congestion, and air freight that eats the entire margin.
This is the calendar we work to with our own customers, written backwards from the date the goods need to be on the shop floor.
Start from the on-shelf date
Not the delivery date at the port, and not the date the container is booked. The date the goods have to be priced and displayed. For most European and North American retailers, Christmas stock needs to be in the store or the warehouse by the end of September, with a buffer before the display goes up in early November.
Work backwards from that date:
- Retail floor: late September. Allow a week for unpacking and pricing.
- Warehouse: mid September. Allow for port delays and inland haulage.
- Sea freight: 30-45 days door to door. Longer in the peak weeks of August and September, when space is tight and rollovers are common.
- Production: 25-35 days after sample approval. Longer for flocked trees and hand-painted metal in peak season.
- Sampling: 7-10 days plus your own approval time. Longer for a new mould or a new colour.
Add it up and the order has to be placed in June or early July. That is the whole argument, and everything else on this page follows from it.
What the calendar looks like
January to March: decide the range
Look at what sold and what came back. Reorder the winners, drop the rest. This is also the point to decide whether to add a category: a wreath programme, a metal decor piece, a light-up range. Decisions made now can be sampled before the factories fill up.
April to May: sample and approve
Samples take a week to make and a week to ship, then a week for you to approve. New moulds take longer, sometimes a month. Approve colourways now - a flocked tree, a painted nutcracker and a custom ribbon all depend on a physical approval, and doing it in August is what causes the rush.
Our flocked tree and the 167 cm nutcracker both need a colour approval before production, because both are made to a specific finish rather than pulled from stock.
June to July: place the production order
Deposit paid, production slot booked, packing artwork approved. This is also when the carton plan is finalised, because carton dimensions decide how many pieces fit a container and therefore the freight per unit. A late change to the retail box in August can push a shipment into a second container.
August: production and inspection
Production runs, inspection happens at the packed stage, and carton photos come back for approval. If something is wrong, this is the last month it can be fixed without air freight.
September: ship
Book freight early. The last two weeks of September are the most expensive and the most likely to be rolled. If a shipment slips here, the choice is air freight on part of the order or accepting that some stock arrives after the display date.
October: contingency
Anything still in production in October is an air freight decision. For light, high-value pieces such as jewelry or small light-up items, air can still work. For trees, wreaths and metal decor, the freight will usually exceed the goods value.
Where the timeline usually breaks
Three failures account for most late Christmas shipments:
- Sampling in July. The sample is approved in August, production runs in September, and the goods arrive in November.
- Artwork delays. The retail box print waits for a logo approval, and the whole run waits with it.
- Order changes after production starts. Adding a colourway or changing a carton quantity mid-run resets the schedule.
All three are buyer-side delays, which is why they are worth planning around rather than blaming on the factory.
If you are already late
There are still options, in this order:
- Split the order. Air-freight the pieces that carry the highest margin - jewelry, small decor, gift sets - and ship the bulky items by sea for January sales or next season.
- Switch to stock designs. A stock tree or wreath can ship in days rather than weeks, which buys back a month.
- Move the season. Christmas stock that arrives in December can be sold as pre-season for the following year, or as "Christmas in January" clearance. It is not ideal, but it is better than storing it for eleven months at full cost.
This is exactly why our Christmas range keeps stock designs running alongside made-to-order items: a buyer who is late can still ship something. The tree range and wreath range both show which models are stock and which need production time.
Container planning, and why it belongs in June
Christmas products are bulky, so the constraint is usually volume rather than weight. A 40 ft high cube holds roughly 68 cubic metres, and artificial trees, wreaths and metal decor fill that far faster than a jewelry order would. Two things decide how much you actually get into the container: the carton dimensions and whether the tall pieces ship assembled or knock-down.
This is why the carton plan has to be finalised in June, alongside the order. A retail box that grows by five centimetres in August can reduce the pieces per carton, push the order over the container limit, and force a second booking at peak-season rates. The change looks trivial on a print proof and costs a container on the water.
Booking freight in the peak weeks
Space out of China in the last two weeks of September is the tightest of the year for Christmas cargo. Rates rise, and rollovers - where a booked container is bumped to a later vessel - are common. Three practical responses:
- Book two to three weeks earlier than you think you need. The cost of holding stock for a fortnight is almost always lower than the cost of air freight.
- Ship part of the order earlier. Splitting a programme into two sailings reduces the risk that one delay takes the whole season with it.
- Keep the highest-margin, lowest-volume items for the later sailing. If something has to be air-freighted, it should be the jewelry and small decor, not the trees.
What a good supplier should tell you in June
Production slot, carton dimensions, pieces per carton, total volume, gross weight and the last sailing date that still lands before your shelf date. If those six numbers are not on the quotation, the timeline is a guess. Ask for them in writing, and treat a supplier who cannot produce them as a risk to the whole season rather than to one order.
A one-line summary
If you want Christmas stock on the shelf for the season, place the order in June, approve the sample in May, and decide the range in March. Everything else is logistics.